January 24, 2022 Grading begins

Moving dirt January 31, 2022

Bubbles helps Greenleaf...

Flat earth! February 7, 2022

Kennel Footings February 16, 2022

Center of the kennel February 16, 2022

February 18, 2022

March 10, 2022

March 16, 2022

March 18, 2022

March 30, 2022

Ready for termite spray... inspection and concrete pour for main building slab.

April 20, 2022

Foundation poured for main buildings

May 16, 2022

Door frames and concrete pad in backyard.

March 23, 2022 Walls beginning to go up!

March 26, 2022 Fast progress on walls & doors



June 16. 2022 Progress as walls are finished.
 

June 22-24, 2022 Framing goes up fast!



July 6, 2022 Topping out!

July 7, 2022 Trellis over the entry

August 24, 2022
Doors and windows going in

Roof installed

August 29, 2022
Kennel walls

September 21, 2022
A good day of insulation, light fixtures, doors, eves. 

September 23,  2022

Front yard dig for run off water drain box, fire sprinkler line, backflow move, one side drywall complete pending fire sprinkler inspection, more doors.

October 7, 2022
Epoxy floor in the kennels!

October 11, 2022

Installation of fire sprinkler system & backflow valves ready for plan check. Approved, so full speed ahead! 72% complete!

October 25, 2022

One backflow valve & 6 ft. of pipe put a halt to all work until it's repaired and AC contractor isn't available. Week-long delay.

November 4, 2022

Windows, stucco prep & walls while we wait for sprinkler repair that is promised for tomorrow.

FONBAS Facilities Chair Tom Fischbacher & Site Superintendent Rich Littleton smile in spite of rain projected for next week.

November 5, 2022

Sprinkler valve repairs under way! Priming the block walls in the kennels.

November 10, 2022 - Sprinklers are done!  

November 14, 2022

Back to full speed ahead. Grading for the front yard footings & parking area begins. Painting of kennels, windows installed. Board member Walt Howald & wife Karen stop by to visit.

November 17, 2022
Digging footings in front yard.

Color added to the kennels

November 18, 2022

The trench for 36" footing for 42" front yard wall.... sturdy!  Pour Monday-Tuesday. Expect no work starting Wednesday afternoon for Thanksgiving  holiday.

November 30, 2022

Meet and greet, front yard walls going up!

December 8, 2022

Wall caps, primer paint, and bathroom tile.

Next week sidewalk gets removed for new driveway, leveling of parking area and prep for final concrete pour.

December 22, 2022

Details are coming together

December 28, 2022

Rain! Too much water.  No, we're not adding a swimming pool!

December 28, 2022

Draining

January 6, 2023

Lots of mud outside, but work continues inside on painting,  floors & kennel gates.

January 12, 2023
Tha sun is out again! Playing in the mud,  but the new curb starts today.

January 13, 2023

The curb is done.  Once we finish compacting the parking lot today, rain will be less of an impact.  Hoping to finish the parking lot next week.

January 19, 2023
The BIG Pour - concrete walkways & entry. Parking lot is next!