January 24, 2022 Grading begins
Moving dirt January 31, 2022
Bubbles helps Greenleaf...
Flat earth! February 7, 2022
Kennel Footings February 16, 2022
Center of the kennel February 16, 2022
February 18, 2022
March 10, 2022
March 16, 2022
March 18, 2022
March 30, 2022
Ready for termite spray... inspection and concrete pour for main building slab.
April 20, 2022
Foundation poured for main buildings
May 16, 2022
Door frames and concrete pad in backyard.
March 23, 2022 Walls beginning to go up!
March 26, 2022 Fast progress on walls & doors
June 16. 2022 Progress as walls are finished.
June 22-24, 2022 Framing goes up fast!
July 6, 2022 Topping out!
July 7, 2022 Trellis over the entry
August 24, 2022
Doors and windows going in
Roof installed
August 29, 2022
Kennel walls
September 21, 2022
A good day of insulation, light fixtures, doors, eves.
September 23, 2022
Front yard dig for run off water drain box, fire sprinkler line, backflow move, one side drywall complete pending fire sprinkler inspection, more doors.
October 7, 2022
Epoxy floor in the kennels!
October 11, 2022
Installation of fire sprinkler system & backflow valves ready for plan check. Approved, so full speed ahead! 72% complete!
October 25, 2022
One backflow valve & 6 ft. of pipe put a halt to all work until it's repaired and AC contractor isn't available. Week-long delay.
November 4, 2022
Windows, stucco prep & walls while we wait for sprinkler repair that is promised for tomorrow.
FONBAS Facilities Chair Tom Fischbacher & Site Superintendent Rich Littleton smile in spite of rain projected for next week.
November 5, 2022
Sprinkler valve repairs under way! Priming the block walls in the kennels.
November 10, 2022 - Sprinklers are done!
November 14, 2022
Back to full speed ahead. Grading for the front yard footings & parking area begins. Painting of kennels, windows installed. Board member Walt Howald & wife Karen stop by to visit.
November 17, 2022
Digging footings in front yard.
Color added to the kennels
November 18, 2022
The trench for 36" footing for 42" front yard wall.... sturdy! Pour Monday-Tuesday. Expect no work starting Wednesday afternoon for Thanksgiving holiday.
November 30, 2022
Meet and greet, front yard walls going up!
December 8, 2022
Wall caps, primer paint, and bathroom tile.
Next week sidewalk gets removed for new driveway, leveling of parking area and prep for final concrete pour.
December 22, 2022
Details are coming together
December 28, 2022
Rain! Too much water. No, we're not adding a swimming pool!
December 28, 2022
Draining
January 6, 2023
Lots of mud outside, but work continues inside on painting, floors & kennel gates.
January 12, 2023
Tha sun is out again! Playing in the mud, but the new curb starts today.
January 13, 2023
The curb is done. Once we finish compacting the parking lot today, rain will be less of an impact. Hoping to finish the parking lot next week.
January 19, 2023
The BIG Pour - concrete walkways & entry. Parking lot is next!