January 24, 2022 Grading begins

Moving dirt January 31, 2022

Bubbles helps Greenleaf...

Flat earth! February 7, 2022

Kennel Footings February 16, 2022

Center of the kennel February 16, 2022

February 18, 2022

March 10, 2022

March 16, 2022

March 18, 2022

March 30, 2022

Ready for termite spray... inspection and concrete pour for main building slab.

April 20, 2022

Foundation poured for main buildings

May 16, 2022

Door frames and concrete pad in backyard.

March 23, 2022 Walls beginning to go up!

March 26, 2022 Fast progress on walls & doors



June 16. 2022 Progress as walls are finished.
 

June 22-24, 2022 Framing goes up fast!



July 6, 2022 Topping out!

July 7, 2022 Trellis over the entry

August 24, 2022
Doors and windows going in

Roof installed

August 29, 2022
Kennel walls

September 21, 2022
A good day of insulation, light fixtures, doors, eves. 

September 23,  2022

Front yard dig for run off water drain box, fire sprinkler line, backflow move, one side drywall complete pending fire sprinkler inspection, more doors.